Loudon County, TN — Solar Development Risk Assessment

Local solar ordinance barriers, board sentiment, and utility policies that affect development timelines and risk.

58.1
Risk Grade
Poor
Fast-growing retirement enclave with Watts Bar Lake; shrinking farmland; rising community opposition to large solar; commission increasingly receptive to anti-solar constituents
Assessment Snapshot
Population
54068
State Rank
#42
Compliance
50%
Trajectory
45

Moratorium Status

✓ No Active Moratorium
No specific moratorium information available.

Ordinance & Regulations

Setback Requirements
Under discussion; no codified standard yet
Zoning Mechanism
CUP per SB 2373; decommissioning bond required; setback standards being drafted
Acreage Caps
None formal

Board Sentiment & Political Risk

Sentiment Analysis
Mixed
Basis for Assessment
Growing retirement/residential community raising NIMBY concerns at commission meetings
Political Risk Factors
Worsening
Board Members
County Executive: Estil Bowen | R | 2026; Commission: majority Republican

Grid, Utilities & State Context

Grid Operator
TVA
Utilities
Lenoir City Utilities Board, Tennessee Valley Authority (wholesale)
State Permitting Process
County zoning authority under SB 2373 (2022); conditional use permit or special exception required; decommissioning bond often required; setback standards increasingly codified at county level
State Incentives
Federal ITC eligible; no Tennessee state solar tax credit; TVA Green Power Switch program

Development Activity

Active/Completed Projects
Loudon County Solar (~18 MW, 2021)
Denied/Withdrawn Projects
One application denied by commission 2024 (site sensitivity near Watts Bar Lake)

Explore the Full Tracker