York County, ME — Solar Development Risk Assessment

Local solar ordinance barriers, board sentiment, and utility policies that affect development timelines and risk.

31.1
Risk Grade
Excellent
S ME; Kittery/Saco/Biddeford area; Boston exurb; growing; active solar in agricultural/rural areas; SLODA >20 acres; local zoning; home rule strong
Assessment Snapshot
Population
213,408
State Rank
#6
Compliance
45%
Trajectory
40

Moratorium Status

✓ No Active Moratorium
No Moratorium

Ordinance & Regulations

Setback Requirements
None codified at county level. Municipal CUP/SUP in organized areas; LUPC in unorganized territories.
Zoning Mechanism
Municipal CUP/SUP (organized areas); LUPC permit (unorganized territories).
Acreage Caps
None codified.
Density Caps
None codified.
Spacing Rules
None codified.
Size Restrictions
None codified.

Board Sentiment & Political Risk

Sentiment Analysis
Generally receptive — growing Boston exurb; active solar; SLODA pathway; local zoning in place
Basis for Assessment
S ME; Kittery/Saco/Biddeford area; Boston exurb; growing; active solar in agricultural/rural areas; SLODA >20 acres; local zoning; home rule strong
Political Risk Factors
Improving
Board Members
Robert L. Andrews | R | Dec 2026 (D1) Richard Dutremble | D | Dec 2026 (D2) Justin Chenette | D | Dec 2026 (D3) Donna L. Ring | R | Dec 2028 (D4) Richard Clark | R | Dec 2028 (D5)

Grid, Utilities & State Context

Grid Operator
ISO-NE / Maine (ME) zone — CMP / Versant territory
Utilities
Central Maine Power (CMP/Avangrid), CMP
State Permitting Process
Strong home rule tradition; dual-track permitting in organized municipalities. Maine DEP Site Location of Development Act (SLODA): required for developments >20 acres (catches most utility-scale solar); standards address stormwater, groundwater, wildlife, aesthetics. Natural Resources Protection Act (NRPA): separate DEP permit for projects affecting wetlands, significant wildlife habitat, or other protected natural resources. Local zoning: organized municipalities (most of southern/coastal ME) require local permits in addition to state permits — dual track; a moratorium can be imposed even after state permits issued (unique ME vested rights doctrine). Land Use Planning Commission (LUPC): governs ~10.5 million acres of Unorganized Territory (UT) in northern/remote ME (much of Aroostook, Piscataquis, Somerset, Penobscot, Washington, Franklin, Oxford, Hancock counties). DACF Permit: required for solar ≥5 acres on High-Value Agricultural Land (HVAL) — new, eff. April 20, 2025. Aroostook and Washington counties (far NE): outside ISO-NE footprint; served by Versant Power (Emera). Central ME Power (Avangrid) and Versant Power are Maine's two investor-owned utilities.
State Incentives
Maine RPS: 80% renewable by 2030; 100% by 2050 (LD 1494, enacted 2019). Net Energy Billing (NEB): Maine's community solar program; subscription-based bill credits; Nautilus Solar, Greenbacker, MN8 Energy (formerly Goldman Sachs) are major operators in ME. Maine CEDF (Clean Energy Development Fund): grants for renewable energy projects via MPUC/CEF. Competitive solicitations: multi-state RFPs (ME, CT, MA, VT) for new solar capacity. Utility: Central Maine Power (CMP/Avangrid) serves southern/central ME; Versant Power (EMERA Maine) serves northern ME and Bangor area.

Development Activity

Active/Completed Projects
Nautilus Solar acquired projects in York County (March 2021, PenBay Pilot). Nautilus 31.5 MW portfolio Nov 2025 includes York County array. Greenbacker portfolio includes York County (10-county ME portfolio, Mainebiz). Multiple NEB community solar arrays; York Co. is active development area (suburban Portland/Saco corridor; CMP territory; good ISO-NE access).
Denied/Withdrawn Projects
ME DEP 2024 proposed rules: discourage solar on prime farmland (Bangor Daily News Aug 14 2024). SLODA: DEP review for >20 acres cleared or >3 MW. NRPA: wetlands/stream buffers. LUPC governs unorganized territories (~10.4M acres). Source: ME DEP; SLODA 38 MRSA §481; Bangor Daily News Aug 14 2024

Explore the Full Tracker

View risk assessments for all 3,100+ US counties, compare states, and download detailed ordinance data for your solar development pipeline.

Launch SolarRisk Tracker