Teller County, CO — Solar Development Risk Assessment

Local solar ordinance barriers, board sentiment, and utility policies that affect development timelines and risk.

50.6
Risk Grade
Fair
Colorado Springs exurban community with strong organized opposition to utility-scale solar; conservative county board; CUP process used to block development; mountainous terrain limits viable sites
Assessment Snapshot
Population
25388
State Rank
#44
Compliance
55%
Trajectory
62

Moratorium Status

✓ No Active Moratorium
No specific moratorium information available.

Ordinance & Regulations

Setback Requirements
200 ft from non-participating residences
Zoning Mechanism
Conditional Use Permit (county planning commission)
Acreage Caps
No formal cap, but CUP discretionary
Density Caps
No
Spacing Rules
None specified
Size Restrictions
<50 MW county CUP; >50 MW CEO review

Board Sentiment & Political Risk

Sentiment Analysis
Opposed — Colorado Springs exurb with organized solar opposition; conservative rural identity
Basis for Assessment
Teller County BOCC minutes; Pikes Peak Courier coverage; public petitions against solar
Political Risk Factors
Worsening
Board Members
Erik Stone (R, 2026) | Marc Dettenrieder (R, 2027) | Norm Steen (R, 2026)

Grid, Utilities & State Context

Grid Operator
Xcel Energy (PSCO) / Black Hills Energy / WECC
Utilities
Xcel Energy (PSCO), Black Hills Energy
State Permitting Process
County zoning; HB 23-1232 CEO review >50 MW; decommissioning bond required
State Incentives
Federal ITC; Colorado Clean Energy Fund; Xcel RE procurement programs

Development Activity

Active/Completed Projects
None — no utility-scale solar approved in county
Denied/Withdrawn Projects
Teller Solar Farm concept (20 MW) withdrawn 2023 after organized opposition

Explore the Full Tracker