Pueblo County, CO — Solar Development Risk Assessment

Local solar ordinance barriers, board sentiment, and utility policies that affect development timelines and risk.

47.9
Risk Grade
Fair
Transition city (former steel); Black Hills/Xcel dual utility territory adds complexity; flat southern and eastern portions ideal for solar; moderate regulatory framework; growing pipeline
Assessment Snapshot
Population
168424
State Rank
#43
Compliance
48%
Trajectory
48

Moratorium Status

✓ No Active Moratorium
No specific moratorium information available.

Ordinance & Regulations

Setback Requirements
150 ft from non-participating residences; 50 ft from public roads
Zoning Mechanism
Special Use Permit (county planning commission)
Acreage Caps
No formal cap
Density Caps
No
Spacing Rules
None specified
Size Restrictions
<50 MW county SUP; >50 MW CEO review

Board Sentiment & Political Risk

Sentiment Analysis
Mixed — Pueblo City pro-solar (clean industry); county rural areas more cautious; union labor preference issues
Basis for Assessment
Pueblo Chieftain coverage; county planning records; Pueblo Economic Development Corporation
Political Risk Factors
Neutral
Board Members
Chris Wiseman (D, 2026) | Garrison Ortiz (D, 2027) | Sal Pace (D, 2026)

Grid, Utilities & State Context

Grid Operator
Black Hills Energy / Xcel Energy (PSCO) / SPP-WECC
Utilities
Black Hills Energy, Xcel Energy (PSCO)
State Permitting Process
County zoning; HB 23-1232 CEO review >50 MW; decommissioning bond required
State Incentives
Federal ITC; Colorado Clean Energy Fund; Xcel RE procurement programs

Development Activity

Active/Completed Projects
Pueblo Solar I (20 MW, 2020); Meadowbrook Solar (35 MW, 2022); San Carlos Solar (~15 MW, 2023)
Denied/Withdrawn Projects
None formally denied