Benton County, AR — Solar Development Risk Assessment

Local solar ordinance barriers, board sentiment, and utility policies that affect development timelines and risk.

62.8
Risk Grade
Poor
Fast-suburbanizing NW Arkansas; enhanced solar ordinance with strict setbacks; suburban encroachment reducing viable rural land; mixed political sentiment; OG&E/SPP queue timelines
Assessment Snapshot
Population
279141
State Rank
#37
Compliance
58%
Trajectory
55

Moratorium Status

✓ No Active Moratorium
No specific moratorium information available.

Ordinance & Regulations

Setback Requirements
500 ft property line; 750 ft occupied structures; 1,000 ft residential subdivisions
Zoning Mechanism
Conditional Use Permit (CUP) - Planning Board; public hearing mandatory; county judge approval
Acreage Caps
None established; suburban growth constraining rural land
Density Caps
None formal
Spacing Rules
None established
Size Restrictions
No projects >50 MW without county judge approval

Board Sentiment & Political Risk

Sentiment Analysis
Mixed - suburban growth concerns; some rural landowner support
Basis for Assessment
Planning board minutes; NW Arkansas Democrat-Gazette; ordinance development process
Political Risk Factors
Worsening
Board Members
County Judge Barry Moehring (R); 15-member Quorum Court - benton.ar.gov

Grid, Utilities & State Context

Grid Operator
SPP / Oklahoma Gas & Electric (OG&E)
Utilities
Oklahoma Gas & Electric (OG&E), Carroll Electric Cooperative
State Permitting Process
County zoning authority; Act 827 sets minimum ANRC standards; conditional use permit or special exception required; decommissioning bond required; setback minimums set by ANRC
State Incentives
Federal ITC eligible; no Arkansas state solar tax credit; Act 827 ANRC framework

Development Activity

Active/Completed Projects
Benton County Solar (40 MW, 2021); Bentonville Solar Farm (28 MW, 2022); NW AR Solar (35 MW, 2023); Rogers Solar (20 MW, 2022); Pea Ridge Solar (15 MW, 2023)
Denied/Withdrawn Projects
Centerton Solar (50 MW, 2023 - denied suburban proximity)